Calgary green LRT

Consortium named for Green Line LRT

Thursday, May 11, 2023

Bow Transit Connectors (BTC) has been selected as the Green Line LRT development partner in Calgary.

BTC brings together Barnard Constructors of Canada, LP, Flatiron Constructors Canada Ltd, and WSP Canada Inc, along with their financial advisor EllisDon Capital Inc. Collectively they will bring shared expertise in underground, above-ground structures, and LRT design and construction to deliver Phase 1 of the Green Line LRT Project.

“The selection of our development partner and launch of the development phase is an important milestone as we move forward with BTC to design, build and finance the Green Line LRT. The Green Line Board has confidence in BTC and their ability to work collaboratively as we collectively ensure we balance costs and risks with the long-term city shaping benefits of Green Line” said Don Fairbairn, chair, Green Line Board.

At 18-kms, Phase 1 is the longest LRT project and largest infrastructure investment in Calgary’s history, creating almost 20,000 jobs throughout construction, $2.2B in long-term city-shaping benefits and more than $6B in property value uplift by 2040.

“As part of the Bow Transit Connectors team, we look forward to bringing our expertise in delivering large scale transportation projects to the Green Line LRT Project. We are proud to share the trust of the City of Calgary as we significantly improve mobility for Calgarians” said Ken Tanner, VP of operations for Flatiron Constructors.

The first phase of the project will have 13 stations, including four underground stops downtown and two elevated stations in the southeast.

The development phase will include design work and agreement on project costs, risks and schedule between the city and BTC before a project agreement is signed.

As part of negotiations, Green Line agreed to extend the development phase from approximately 12 months to 16 months to allow for greater design progression and cost certainty. The implementation phase remains on track to begin in 2024.

 